|
NGSDH and Access system and Fiber optic Telecommunication Link Between Damavand Power Plant and Rey Power Plant
Enduser:
Iran Power Development Company (IPDC)
Progress Percentage:
100%
Ray Avin Fan Services:
Engineering
Procurement
Factory Acceptance Test
Supervision on Installation
Site Acceptance and Commissioning
Training
Project Description:
Qualification and awarding this project through tendering procedure and investigation to prepare required optical fiber communication system for Damavand Power Plant as the biggest Power Plant in Middle East, is one of our brilliant successes in our done projects as well.
At the time of project this project was very important and in top urgent classification and we could complete our scope of work very earlier than others. As soon as completion of other companies scope of work in passive parts of projects our system start to work and from that time it is in service.
Very soon this point became one of the most important communication nodes based on its place of work that is one of critical communication bottle necks in TAVANIR. Nowadays all traditional communication traffic for PABX and PLC (Power Line Carrier) systems at that area is supported by prepared required interfaces with installed system such as Djalal Substation PAX connection up to Social Operation Center, same for Ahowan Substation including its DTS, required SOC data transfer through Analog Modems received from PLC system, Preparing required Data Tunnel to support Ethernet network to build WAN in cooperation with Tehran Regional Electrical Co. in Sadat Abad Building that support both their computer network and internet, Forwarding all SCADA data to SOC from Damavand P.P and 400KV substation, Ahowan 400 KV Substation and Damghan 400KV Substation.
On time activities and good project management make end user to award us official letter about our good performance action.
Specification:
- • STM-1 NG-SDH
- • Access
- - FXO ab wire port
- - FXS ab wire port
- - E1 G703 port
- - Ethernet/Fast Ethernet 10/100 BaseT peer to peer connection port
- - E&M 4/6 wire port suitable for usage as trunk between central units, Analogue Modem connection, Power Line Carrier system (PLC), DTS
- - Rectifier Charger and batteries in -48VDC
- - Supplying required spare parts
OPGW installation over Live and Dead 400 kV Line from Taghideezaj Substation to Azarbayjan Border
Enduser:
Iran Power Development Company (IPDC)
Progress Percentage:
100%+25%
Ray Avin Fan Services:
Partial Procurement
Live line installation
Dead line installation
Test and Commissioning
Project Description:
Installation of Optical Guard Wires over 150 km of 400kv line with metal lathetic and none metal towers between Ardebil(Sabalan) power plant and Azerbaijan border in fully outage condition was the scope of work.
Based on tight time schedule for installation and many difficulties to prepare required outages we prepare a letter to suggest our client to let us to work in Live Line condition and Install OPGW over all crossings with 20kv, 63kv, 230kv and 400kv lines.
With our client acceptance and preparing required permit we start to work in Live Line condition and succeed to complete our scope of work before due date. In this regards the client issues attached official letter of our good performance activities also.
Specification:
Installation Single layer OPGW 10.5 mm overall diameter with NZDSF fibers in both getting outage and Live parts of HV Lines
Services:
Procurement required: OCDF, Direct Burial Optical Cable, Pigtail
Commissioning
Provisional Acceptance Test and Final acceptance test
OPGW installation over Live 400 kV Line from Choghadak Substation to Omidiyeh II Substation and from Omidiyeh II to Karoun III Substation
Enduser:
Iran Power Development Company (IPDC)
Progress Percentage:
100%+20%
Ray Avin Fan Services:
Partial Procurement
Repairing already installed parts in older sections
Full Live line installation of new section
Test and Commissioning
Project Description:
Full Live Line Installation of Optical Guard Wires over 120 km of 400kv line with metal lathetic between Chogadak SS and Omidiyeh II SS as first section and Omidiyeh II - Karoun III as second section.
We complete first step of contract and start site mobilization and are waiting for required permit to start our activities.
Specification:
Installation two layer OPGW 15mm overal diameter and Single layer OPGW 12 mm overall diameter with NZDSF fibers in Live 400kv HV Lines
Services:
Procurement required OCDF, Direct Burial Optical Cable, Pigtail
Commissioning
Provisional Acceptance Test and Final acceptance test
NGSDH and Access system and Fiber optic Telecommunication Link Between Ardebil(Sabalan) Power Plant and Taghidizaj Substation
Enduser:
Iran Power Development Co.- Azarbayejan Regional Electric Co.
Progress Percentage:
100%+25%
Ray Avin Fan Services:
Engineering
Procurement
Construction
Factory Acceptance Test
Commissioning
Training
Project Description:
This project has same characteristics to our older project in Damavand in scope of work and end user requirements and also is in contract negotiations and exchange stage now.
Specification:
- • STM-1 NG-SDH
- • Access
- - FXO ab wire port
- - FXS ab wire port
- - E1 G703 port
- - Ethernet/Fast Ethernet 10/100 BaseT peer to peer connection port
- - E&M 4/6 wire port suitable for usage as trunk between central units, Analogue Modem connection, Power Line Carrier system (PLC), DTS
- - Rectifier Charger and batteries in -48VDC
OPGW installation over Live 230 kV Line from Khoy PP to Orumiyeh II Substation and from Orumiyeh II substation to Orumiyeh PP
Enduser:
Iran Power Development Co.- Azarbayejan Regional Electric Co.
Progress Percentage:
100%
Ray Avin Fan Services:
Partial Procurement
Reforming existing GW cross arms to be able to adjust them to new OPGW accessories
Full Live line installation
Test and Commissioning
Project Description:
Full Live Line Installation of Optical Guard Wires over 167 km of 230kv line with 59 metal lathetic towers and 510 concreat towers between
Khoy PP to Orumiyeh II Substation as first part and from Orumiyeh II substation to Orumiyeh PP as second part
The progress in first part considering of completion of second part with 69 towers is around 62% and estimated time for total completion is less than one month.
Specification:
Installation Single layer OPGW 12 mm overall diameter with NZDSF fibers in Live 230kv HV Lines
Services:
Procurement required accessories
Commissioning
Provisional Acceptance Test and Final acceptance test
NGSDH and Access system and Fiber optic Telecommunication Link Between Khoramshahr Power Plant and Abadan Milad Substation
Enduser:
Iran Power Development Company (IPDC)
Progress Percentage:
100%
Ray Avin Fan Services:
Engineering
Procurement
Factory Acceptance Test
Supervision on Installation
Site Acceptance and Commissioning
Training
Project Description:
Project Description:
This project has same characteristics to our older project in Damavand in scope of work and end user requirements and also is in contract negotiations and exchange stage now.
Specification:
- • STM-1 NG-SDH
- • Access
- - FXO ab wire port
- - FXS ab wire port
- - E1 G703 port
- - Ethernet/Fast Ethernet 10/100 BaseT peer to peer connection port
- - E&M 4/6 wire port suitable for usage as trunk between central units, Analogue Modem connection, Power Line Carrier system (PLC), DTS
- - Rectifier Charger and batteries in -48VDC
NGSDH and Access system and Fiber optic Telecommunication Link Between Kashan Power Plant and Kashan Ravand Substation
Enduser:
Iran Power Development Co.
Progress Percentage:
100%
Ray Avin Fan Services:
Engineering
Procurement
Construction
Factory Acceptance Test
Commissioning
Training
Project Description:
This project has same characteristics to our older project in Damavand in scope of work and end user requirements and also is in contract negotiations and exchange stage now.
Specification:
- • STM-1 NG-SDH
- • Access
- - FXO ab wire port
- - FXS ab wire port
- - E1 G703 port
- - Ethernet/Fast Ethernet 10/100 BaseT peer to peer connection port
- - E&M 4/6 wire port suitable for usage as trunk between central units, Analogue Modem connection, Power Line Carrier system (PLC), DTS
- - Rectifier Charger and batteries in -48VDC
NGSDH and Access system and Fiber optic Telecommunication Link Between Aliabad Power Plant and Substation
Enduser:
Iran Power Development Co.
Progress Percentage:
Contract negotiation.
Ray Avin Fan Services:
Engineering
Procurement
Construction
Factory Acceptance Test
Commissioning
Training
Project Description:
This project has same characteristics to our older project in Kashan in scope of work and end user requirements and also is in contract negotiations and exchange stage now.
Specification:
- • STM-1 NG-SDH
- • Access
- - FXO ab wire port
- - FXS ab wire port
- - E1 G703 port
- - Ethernet/Fast Ethernet 10/100 BaseT peer to peer connection port
- - E&M 4/6 wire port suitable for usage as trunk between central units, Analogue Modem connection, Power Line Carrier system (PLC), DTS
- - Rectifier Charger and batteries in -48VDC
|